Schedule of Rates vs Bill of Quantities: What’s the Difference?

A schedule of rates lists agreed unit prices with no quantities. A bill of quantities, by contrast, lists every measured quantity, priced line by line to a total. That one difference changes who carries the measurement risk, how tenders are compared, and how you get paid. Here is how each document works, where each fits, and the mistakes that cost contractors money under both.

What Is a Schedule of Rates?


schedule of rates document with unit prices and no quantities

A schedule of rates is a list of work items with an agreed price per unit. Think per cubic metre, per square metre, per hour or per fixture. Crucially, it states no quantities. The client and contractor agree the rates upfront, and payment follows the quantities actually measured once the work is done.

How a Schedule of Rates Contract Works

The contractor tenders rates against a list of expected work types. Next, completed work is measured, valued at the scheduled rates, and claimed. Consequently, there is no fixed contract sum: the final cost is simply measured quantity multiplied by rate, item by item.

When a Schedule of Rates Is Used

SOR contracts dominate wherever scope cannot be fixed in advance: term maintenance agreements, repair panels, emergency works and minor works programs. For example, many state and council panels operating under NSW Government procurement arrangements engage contractors on scheduled rates. After all, nobody knows in January which pipes will burst in June.

The Risk Contractors Miss

Under an SOR, your rate is your margin. A rate priced 5% light on a 12-month maintenance panel repeats that loss on every single work order. Worse, there is no lump sum buffer to hide it. Therefore, rates need building from first principles: labour, plant, materials, overheads and margin. Our construction estimating services build rates exactly this way, so the number you commit to for a year actually holds.

What Is a Bill of Quantities?


bill of quantities with measured quantities prepared from drawings

A bill of quantities is a complete, itemised list of everything a project requires. Every item is measured from the drawings and priced line by line to a total contract sum. Reliable quantities start with a proper measurement of the plans. That is why our takeoff estimating services sit underneath every bill we produce.

How a Bill of Quantities Works

The bill is structured by trade or element: excavation, concrete, carpentry, finishes and so on. Each line carries a description, a measured quantity, a unit, a rate and an amount. As a result, the totals roll up to a lump sum that both parties can rely on before a shovel hits the ground.

When a Bill of Quantities Is Used

BOQs are the standard for tendered projects with a complete design: residential builds, commercial fitouts and government lump sum work. Because every bidder prices identical quantities, the client can compare tenders line by line. Meanwhile, the contractor knows exactly what the price includes.

Here is the same work item as it appears in each document. Notice that the rate is identical; the difference is entirely in the quantity and the certainty of the amount.

DocumentItem descriptionQuantityUnitRateAmount
Schedule of ratesExcavate trench in natural groundNot stated (re-measured)m3$85.00Determined on measurement
Bill of quantitiesExcavate trench in natural ground240m3$85.00$20,400.00

Key Differences Between the Two Documents


The table below summarises how the two documents behave across the factors that matter most when you are choosing a contract structure.

FactorSchedule of rates (SOR)Bill of quantities (BOQ)
QuantitiesNot stated; work is re-measured as it proceedsFully measured from the drawings before pricing
Contract priceNo fixed total; the final cost follows measurementLump sum known at contract award
Risk allocationClient carries quantity risk; contractor carries rate riskQuantity risk sits with whoever prepared the bill
Best suited toMaintenance, term and repair contracts with undefined scopeTendered projects with complete design
PaymentProgress claims on measured completed workStaged claims against the priced bill
Tender comparisonRates compared line by line across biddersTotals and rates compared directly
Admin burdenOngoing re-measurement and valuationHeavier upfront, lighter during construction

The risk row deserves emphasis. Under an SOR, if quantities blow out, the client pays more but your rates still hold. However, under a BOQ, a missed or under-measured quantity comes out of someone’s margin. As a result, the accuracy of the takeoff behind the bill decides who wins and who bleeds.

Which One Should You Use?


choosing between a schedule of rates and a bill of quantities

Choose a Schedule of Rates When

The scope cannot be defined upfront. Term maintenance, repair panels, reactive works and long-running minor works programs all fit here. Similarly, early contractor engagements sometimes run on scheduled rates while the design is still moving.

Choose a Bill of Quantities When

The design is complete and you are pricing a defined project. A measured bill gives you a defendable lump sum and protects you in tender comparisons. Later, it also becomes the backbone of your progress claims. For formal submissions, our tender estimating services deliver the priced bill in the format the procurement team expects.

When You Need Both

Australian contracts frequently combine the two. Under standard forms such as AS 4000, published by Standards Australia, a lump sum project commonly attaches a schedule of rates. In that case, the rates exist purely for pricing variations and provisional work. In other words, the bill fixes the known scope and the rates handle the unknowns. For most projects, that is the cleanest risk split of all.

Not sure how to produce these documents in the first place? Our guide to estimating for builders compares doing it yourself, using software and outsourcing.


Frequently Asked Questions

A schedule of rates contract is an agreement where the contractor commits to unit prices for defined work types. Payment then follows the quantities actually measured as work proceeds. There is no fixed contract sum. It is the standard structure for maintenance panels, term contracts and repair work across Australia.

Both are Australian Standard general conditions of contract for construction. AS 2124 dates from 1992. AS 4000 then replaced it in 1997 with a plain-English drafting style and a rebalanced risk allocation. Importantly, both forms can operate as lump sum contracts, schedule of rates contracts, or a combination of the two.

The four most common types in Australia are lump sum, schedule of rates, cost plus, and design and construct. A lump sum fixes the price for a defined scope. A schedule of rates re-measures quantities at agreed unit prices. Cost plus recovers actual costs plus a margin, while design and construct puts design and delivery under one contractor. Each allocates risk differently.

Builder charge-out rates typically range from around $70 to $120 or more per hour. The figure varies with state, licensing and project type. However, a schedule of rates rarely prices work by the hour alone. Instead, it converts labour, materials, plant and margin into a rate per unit of finished work, such as per square metre.

Construction uses cost schedules and time schedules. Cost schedules, including the schedule of rates and the priced bill of quantities, define what work costs. Time schedules, often called construction programs, define when work happens. The L1 to L4 schedules you may see referenced belong to programming, not pricing.

A schedule is an attachment that forms part of the contract documents. It carries the detail the main terms refer to, such as rates, scope descriptions, key dates or special conditions. If a rate appears in a contract schedule, it is legally binding. Accordingly, the numbers in it deserve the same care as the contract itself.

Yes. Our Australian-based estimators prepare measured bills of quantities from your drawings and build schedule of rates pricing from first principles. Both are aligned to your labour rates and margins. You typically receive the completed document within 3 to 5 business days. There are no lock-in contracts, and your first estimate is risk-free.


The Bottom Line on the Schedule of Rates

A schedule of rates prices the unknown; a bill of quantities prices the known. Choose the SOR when scope cannot be fixed, and choose the BOQ when the design is complete. Then combine them when a lump sum job needs a clean mechanism for variations. Either way, the document is only as strong as the measurement and rate-building behind it. Build Metric delivers professional estimating services for contractors across Australia. In every document, you get measured quantities, first-principles rates and our Triple Guarantee across win rate, delivery and accuracy.

Table of Contents

Share on Social Media

About the Author

Luke Rose | Founder, Build Metric

Luke Rose founded Build Metric to give Australian builders professional-grade estimating without the cost of a full-time hire. The Build Metric team has delivered over 1,500 estimates across residential and commercial construction nationally, backed by 100+ years of combined industry experience.

Related Posts

Have a question or need estimating support?

BEST WP THEME

All Demos Included

All Demos Included with this amazing WordPress Theme you will have everything you need to create a memorable and enchanting online presence. Start create your dream site today.

Orange Right Arrow 4

Our team delivers reliable solutions tailored to your specific needs. We prioritize quality and customer satisfaction in every project.

Address :

Info :