A schedule of rates lists agreed unit prices with no quantities. A bill of quantities, by contrast, lists every measured quantity, priced line by line to a total. That one difference changes who carries the measurement risk, how tenders are compared, and how you get paid. Here is how each document works, where each fits, and the mistakes that cost contractors money under both.
Key Takeaways
- A schedule of rates (SOR) prices work by unit rates only, and quantities are measured as the work proceeds.
- A bill of quantities (BOQ) itemises measured quantities from the drawings and prices them to a fixed contract sum.
- SOR contracts suit maintenance, term and repair work where the scope cannot be fixed upfront.
- BOQ contracts suit tendered projects with complete design, giving price certainty and easy bid comparison.
- Under an SOR the client carries the quantity risk; under a BOQ the quantity risk follows whoever prepared the bill.
- Build Metric prepares both documents. Our bill of quantities preparation gives Australian contractors measured, tender-ready bills without the in-house workload.
What Is a Schedule of Rates?

A schedule of rates is a list of work items with an agreed price per unit. Think per cubic metre, per square metre, per hour or per fixture. Crucially, it states no quantities. The client and contractor agree the rates upfront, and payment follows the quantities actually measured once the work is done.
How a Schedule of Rates Contract Works
The contractor tenders rates against a list of expected work types. Next, completed work is measured, valued at the scheduled rates, and claimed. Consequently, there is no fixed contract sum: the final cost is simply measured quantity multiplied by rate, item by item.
When a Schedule of Rates Is Used
SOR contracts dominate wherever scope cannot be fixed in advance: term maintenance agreements, repair panels, emergency works and minor works programs. For example, many state and council panels operating under NSW Government procurement arrangements engage contractors on scheduled rates. After all, nobody knows in January which pipes will burst in June.
The Risk Contractors Miss
Under an SOR, your rate is your margin. A rate priced 5% light on a 12-month maintenance panel repeats that loss on every single work order. Worse, there is no lump sum buffer to hide it. Therefore, rates need building from first principles: labour, plant, materials, overheads and margin. Our construction estimating services build rates exactly this way, so the number you commit to for a year actually holds.
What Is a Bill of Quantities?

A bill of quantities is a complete, itemised list of everything a project requires. Every item is measured from the drawings and priced line by line to a total contract sum. Reliable quantities start with a proper measurement of the plans. That is why our takeoff estimating services sit underneath every bill we produce.
How a Bill of Quantities Works
The bill is structured by trade or element: excavation, concrete, carpentry, finishes and so on. Each line carries a description, a measured quantity, a unit, a rate and an amount. As a result, the totals roll up to a lump sum that both parties can rely on before a shovel hits the ground.
When a Bill of Quantities Is Used
BOQs are the standard for tendered projects with a complete design: residential builds, commercial fitouts and government lump sum work. Because every bidder prices identical quantities, the client can compare tenders line by line. Meanwhile, the contractor knows exactly what the price includes.
Here is the same work item as it appears in each document. Notice that the rate is identical; the difference is entirely in the quantity and the certainty of the amount.
| Document | Item description | Quantity | Unit | Rate | Amount |
|---|---|---|---|---|---|
| Schedule of rates | Excavate trench in natural ground | Not stated (re-measured) | m3 | $85.00 | Determined on measurement |
| Bill of quantities | Excavate trench in natural ground | 240 | m3 | $85.00 | $20,400.00 |
Key Differences Between the Two Documents
The table below summarises how the two documents behave across the factors that matter most when you are choosing a contract structure.
| Factor | Schedule of rates (SOR) | Bill of quantities (BOQ) |
|---|---|---|
| Quantities | Not stated; work is re-measured as it proceeds | Fully measured from the drawings before pricing |
| Contract price | No fixed total; the final cost follows measurement | Lump sum known at contract award |
| Risk allocation | Client carries quantity risk; contractor carries rate risk | Quantity risk sits with whoever prepared the bill |
| Best suited to | Maintenance, term and repair contracts with undefined scope | Tendered projects with complete design |
| Payment | Progress claims on measured completed work | Staged claims against the priced bill |
| Tender comparison | Rates compared line by line across bidders | Totals and rates compared directly |
| Admin burden | Ongoing re-measurement and valuation | Heavier upfront, lighter during construction |
The risk row deserves emphasis. Under an SOR, if quantities blow out, the client pays more but your rates still hold. However, under a BOQ, a missed or under-measured quantity comes out of someone’s margin. As a result, the accuracy of the takeoff behind the bill decides who wins and who bleeds.
Which One Should You Use?

Choose a Schedule of Rates When
The scope cannot be defined upfront. Term maintenance, repair panels, reactive works and long-running minor works programs all fit here. Similarly, early contractor engagements sometimes run on scheduled rates while the design is still moving.
Choose a Bill of Quantities When
The design is complete and you are pricing a defined project. A measured bill gives you a defendable lump sum and protects you in tender comparisons. Later, it also becomes the backbone of your progress claims. For formal submissions, our tender estimating services deliver the priced bill in the format the procurement team expects.
When You Need Both
Australian contracts frequently combine the two. Under standard forms such as AS 4000, published by Standards Australia, a lump sum project commonly attaches a schedule of rates. In that case, the rates exist purely for pricing variations and provisional work. In other words, the bill fixes the known scope and the rates handle the unknowns. For most projects, that is the cleanest risk split of all.
Not sure how to produce these documents in the first place? Our guide to estimating for builders compares doing it yourself, using software and outsourcing.
Get Your Estimate Ready
- Need a priced schedule or a measured bill for a live job? Upload your plans and get your first estimate from Build Metric, risk-free, or call 1300 819 112.
Frequently Asked Questions
A schedule of rates contract is an agreement where the contractor commits to unit prices for defined work types. Payment then follows the quantities actually measured as work proceeds. There is no fixed contract sum. It is the standard structure for maintenance panels, term contracts and repair work across Australia.
Both are Australian Standard general conditions of contract for construction. AS 2124 dates from 1992. AS 4000 then replaced it in 1997 with a plain-English drafting style and a rebalanced risk allocation. Importantly, both forms can operate as lump sum contracts, schedule of rates contracts, or a combination of the two.
The four most common types in Australia are lump sum, schedule of rates, cost plus, and design and construct. A lump sum fixes the price for a defined scope. A schedule of rates re-measures quantities at agreed unit prices. Cost plus recovers actual costs plus a margin, while design and construct puts design and delivery under one contractor. Each allocates risk differently.
Builder charge-out rates typically range from around $70 to $120 or more per hour. The figure varies with state, licensing and project type. However, a schedule of rates rarely prices work by the hour alone. Instead, it converts labour, materials, plant and margin into a rate per unit of finished work, such as per square metre.
Construction uses cost schedules and time schedules. Cost schedules, including the schedule of rates and the priced bill of quantities, define what work costs. Time schedules, often called construction programs, define when work happens. The L1 to L4 schedules you may see referenced belong to programming, not pricing.
A schedule is an attachment that forms part of the contract documents. It carries the detail the main terms refer to, such as rates, scope descriptions, key dates or special conditions. If a rate appears in a contract schedule, it is legally binding. Accordingly, the numbers in it deserve the same care as the contract itself.
Yes. Our Australian-based estimators prepare measured bills of quantities from your drawings and build schedule of rates pricing from first principles. Both are aligned to your labour rates and margins. You typically receive the completed document within 3 to 5 business days. There are no lock-in contracts, and your first estimate is risk-free.
The Bottom Line on the Schedule of Rates
A schedule of rates prices the unknown; a bill of quantities prices the known. Choose the SOR when scope cannot be fixed, and choose the BOQ when the design is complete. Then combine them when a lump sum job needs a clean mechanism for variations. Either way, the document is only as strong as the measurement and rate-building behind it. Build Metric delivers professional estimating services for contractors across Australia. In every document, you get measured quantities, first-principles rates and our Triple Guarantee across win rate, delivery and accuracy.